Here you specify the Type of the BOM component you are about to create. You can choose between the following options:
Type |
Function |
Blank |
If you leave this field empty, the line will be interpreted as text. |
Item |
The line will be interpreted as material consumption per unit with the
No. field referring
to an Item No..
The Item can have a BOM itself. |
Setup |
The No. field refers to an Operation of the Type Setup. Setup is labor with a cost per Production Order independent of the order quantity. By posting it will be added to the production cost. |
Operation |
The No. field refers to an Operation of the Type Operation. An Operation has a cost per minute which will be added to the production cost by posting. |
Sub-supplier Work |
The No. field refers to an Operation of the Type Sub-supplier Work. Sub-supplier work has a cost per unit which will be added to the production cost by posting. |
Matrix |
This option is only used in connection with automatic creation of Assortments. |
Important:
The sequence of the BOM Component Lines describes the routing of the
production process. The flow goes from top to bottom and Operations can
be set up to post material consumption of above lines automatically. Therefore it is
very important that you place the BOM Component Lines in correct order.